Replacement of the site main switchboard.

THE PROJECT

Replacement of the site main switchboard

Foster’s Services were commissioned to replace the existing aged electrical switchboard infrastructure and the auto transfer switch assembly for the site generator, and to install a large generator set to provide for future capacity and meet licensing guidelines.

All aspects of the changeovers onto the new switchboard were completed with a special focus on patient care, staffing needs and minimising outage durations.

Thanks to detailed, future-proof planning, the final product is an installation that will support the needs of the hospital for decades to come.

St John of God Mt Lawley Hospital, MEA Commercial Project of the Year (WA) 2021 winner

PROJECT DETAILS

What we delivered

  • Installation of new site switchboard and infrastructure
  • No unplanned outages to site power and little disruption to hospital operations
  • Detailed investigation of the existing electrical installation
  • Installation and commissioning of the hospital-supplied 700 kVA diesel standby generator
  • Supply and installation of new site main switchboard
  • Disconnection and disposal of the existing generator, co-generator and site main switchboard
  • New automatic source transfer facilities for transition from mains to generator supply
  • Liaison with Western Power for changeover of switchboard and metering facilities
  • New submains power supplies to locations including medical clinics, and rising mains changes
  • Extension of existing submains cabling
  • Builders works to achieve a 2-hour fire rating for the existing electricians’ storeroom to become the new LV main switch room
  • Testing and commissioning

At a glance

Client

St John of God Mt Lawley Hospital

Award

MEA Commercial Project of the Year (WA) 2021

Generator

700 kVA diesel standby

Outages

No unplanned outages to site power

“What stood out about this project was the attention to detail, planning and risk mitigation needed for such an important project. The relationship with all parties, the communication and consultation had this project as a leader in this award.”

Judging panel, 2021 Electrical Industry Excellence Awards, Master Electricians Australia

GALLERY

Project photos

More projects

Armadale Hospital main entrance

HEALTHCARE · COMMERCIAL ELECTRICAL

Armadale Hospital

A $2 million electrical modernisation for Armadale Hospital on behalf of East Metro Health Service, upgrading the entire power infrastructure for campus-wide resilience against total mains failure.

Bethesda Hospital entrance

HEALTHCARE · COMMERCIAL ELECTRICAL

Bethesda Hospital

Working with Stantec Engineering and Price Trandos Switchboards, a complex main switch room replacement and relocation project for Bethesda Hospital.

Peel Health Campus entrance

HEALTHCARE · COMMERCIAL ELECTRICAL

Peel Health Campus

An essential services switchboard upgrade and generator replacement project for the Peel Health Campus.

SERVICING WESTERN AUSTRALIA

From Broome to Perth to Esperance and everywhere in between

Our highly skilled team has the skills, experience, equipment, workforce and network to support your project across our vast state.

We work across the Perth metro area, Peel, the South West, Great Southern, Wheatbelt, Goldfields-Esperance, Mid West, Gascoyne, Pilbara and Kimberley.

Head office · 19 Parkinson Lane, Kardinya WA 6163

Statewide · metro, regional and remote sites across WA

24/7 after hours · 1300 19 19 42

Kununurra Broome Port Hedland Karratha Geraldton Kalgoorlie Esperance Albany Perth Head office, Kardinya WESTERN AUSTRALIA

Got a project you’d like to discuss?

Tell us about your site and our team will be in touch.